ANAVA SAMUI | Latest Project Progress (September 30, 2026)
Steadfast dedication, transformative milestones. ANAVA SAMUI continues to drive site development with uncompromising engineering standards. As September concludes, we have achieved major breakthroughs in architectural finishing and structural execution, including the 100% completion of Building M's main structure!
Sincere thanks to all our valued owners and partners for your continuous trust and support. As of September 30, 2026, the latest construction progress across the site is as follows:
Project Progress as of September 30, 2026:
Building A: Bathroom floor tiling, bathroom glass installation, balcony glass balustrade installation, and balcony aluminum sliding door installation in progress.
Building C: Ceiling grid installation 100% completed.
Building D: Exterior wall plastering and balcony glass balustrade installation in progress.
Building E: Scaffolding dismantling in progress.
Building F: Exterior wall plastering 50% completed.
Building H: Interior wall plastering 50% completed.
Building M: Main structural work 100% completed (Structural topping out).