ANAVA SAMUI | Latest Project Progress (September 15, 2026)

Precision in execution, consistency in excellence. ANAVA SAMUI continues to advance site development with rigorous quality and structural standards, marking key milestones across multiple buildings as your dream island residence steadily takes form.

Sincere appreciation to all our valued owners and partners for your ongoing confidence and support! As of September 15, 2026, the site construction milestones are as follows:

Project Progress as of September 15, 2026:

  • Building C: Interior and exterior wall plastering 100% completed.

  • Building E: Interior wall plastering 100% completed.

  • Building F: Roofing works 100% completed.

  • Building G: Roofing works 100% completed.

  • Building H: Roofing works 100% completed.

  • Building M: Main structural work 70% completed.

Walking with you toward an inspiring chapter of luxury island living in Koh Samui. Stay tuned for further updates!