Latest Project Progress (August 31, 2026)
Crafted with precision, delivered with dedication. ANAVA SAMUI continues to advance construction across all buildings with uncompromising quality and rigorous engineering standards, turning the vision of premier island living into reality.
A heartfelt thank you to all our owners and partners for your ongoing trust and support! As of August 31, 2026, here is the latest building-by-building construction milestone update:
Project Progress as of August 31, 2026:
Building A: Exterior wall coating 95% completed.
Building C: Interior wall plastering 100% completed.
Building D: Exterior wall coating 85% completed.
Building E: Interior wall plastering 100% completed.
Building F: Ceiling grid installation 100% completed.
Building G: Masonry 100% completed.
Building K: Masonry 80% completed.
Building J: Masonry 100% completed.
Building M: Main structural work 35% completed.
Walking hand-in-hand with you toward an extraordinary chapter of luxury island living in Koh Samui. Stay tuned for next month's updates!