Project Progress for June 2026

Welcome to the latest construction update for ANAVA SAMUI, the premier luxury property destination in Koh Samui. As of June 2026, our development is moving forward steadily with high-quality standards. Whether you are looking for an island investment or your dream holiday home in Thailand, discover our month-on-month engineering milestones and see how your future island life is taking shape below.

Project Progress for June 2026:

  • Building L: Main structural topping out completed.
  • Building A: 3rd and 4th-floor plastering 100% completed; exterior wall coating 80% completed.
  • Building C: 4th-floor water supply pipe installation 70% completed.
  • Building D: Interior wall plastering 100% completed; exterior wall plastering 50% completed.
  • Building E: Wall steel wire mesh installation 100% completed.
  • Building F: 4th-floor corridor conduit and cable tray installation 100% completed.
  • Building H: Exterior facade arc formwork installation 100% completed.
  • Building M: 1st-floor ground concrete casting 100% completed.