Project Progress for July 2026
ANAVA SAMUI continues to uphold strict engineering quality and high-standard craftsmanship to steadily advance site construction. Sincere thanks to all owners and partners for your trust and support! As of July 2026, building progress across the site is moving forward in an orderly manner. Below is the detailed building-by-building construction update for July 2026:
- Building A: Exterior wall coating 90% completed.
- Building C: Water supply pipe installation 100% completed.
- Building D: Exterior wall plastering 100% completed.
- Building E: Interior wall plastering 95% completed.
- Building F: 4th-floor ceiling grid / framing installation 50% completed.
Building G: Masonry 90% completed.