ANAVA SAMUI Construction Progress Update - (2026.05.21)

ANAVA SAMUI will continue to uphold high standards and high-quality construction requirements to steadily advance project construction.Sincere thanks to all clients for your continuous attention and support!

ANAVA SAMUIWalking with you to draw a new chapter of island life.

Construction of all buildings is progressing steadily. As of May 21, 2026, the construction progress is as follows:

  • Building L: 3rd-floor roof beam and slab formwork installation completed.
  • Building A: 3rd-floor plastering 90% completed; 2nd-floor bathroom concrete kicker casting completed; exterior wall spatter-dash 50% completed.
  • Building C: Pitched roof concrete casting 100% completed.
  • Building D: 2nd-floor lintel and structural column concrete casting 100% completed.
  • Building H: Masonry 100% completed.
  • Building G: 2nd and 3rd-floor masonry 80% completed.
  • Building F: 4th-floor plastering 80% completed.
  • Sedimentation Tank: Backfilling 100% completed.

Below are the latest on-site construction photos to provide a direct view of the project dynamics:

Building F: 4th-floor plastering

01.png

Building G: 2nd and 3rd-floor masonry

Image

Building H: 4th-floor masonry

Image

Building L: 3rd-floor formwork and scaffolding installation

Building A: 3rd-floor plastering

Image

Building F: 4th-floor plastering

Image

Building A: 2nd-floor bathroom guide wall casting

Image

Building A: 3rd-floor plastering

Image


ANAVA SAMUI will continue to uphold high standards and high-quality construction requirements to steadily advance project construction.

Sincere thanks to all clients for your continuous attention and support!