ANAVA SAMUI Construction Progress Update - (2025.12.26)
Since the official groundbreaking ceremony on April 27th, 2025, the construction of ANAVA SAMUI has been progressing steadily and according to schedule. As of 26 December 2025, the construction updates are as follows:
- Building D: First-floor masonry completed; second-floor masonry approximately 30% completed.
Building G: Fourth-floor slab formwork completed; rebar installation approximately 50% completed.
Building H: Fourth-floor slab concrete pouring completed.
Building J: Ground beam rebar installation completed.
Secondary Structure & MEP (Mechanical, Electrical & Plumbing) Works:
Bathroom guide walls and wall rebar anchoring works: Buildings C, D, E, F: Completed; Buildings A, B: Approximately 50% completed; Building H: Approximately 25% completed.
Ventilation & plumbing works: Ventilation vertical pipes completed in Buildings C, D, E, F; Bathroom piping installation in Building F approximately 80% completed.
Others Works:
West-side boundary wall: Masonry works completed; plastering approximately 50% completed.
Please see the latest on-site construction photos below for a visual update:
Building D: Second-floor wall masonry; formwork for structural columns and ring beams.
Building E: Bathroom guide wall concreting; ventilation vertical pipe installation.
Building F: Drainage installation.
Building G: Fourth-floor internal scaffolding setup; slab formwork and rebar installation.
Building H: Fourth-floor slab concrete pouring.
Building J: Foundation ground beam rebar installation.
ANAVA SAMUI remains committed to maintaining high construction standards and ensuring quality at every stage of the project.
As 2025 comes to an end, we would like to extend our sincere appreciation and warmest wishes to all our clients. May the year ahead bring you good health, happiness, and continued success.
Thank you for your continued trust and support!
ANAVA SAMUI