ANAVA SAMUI Construction Progress Update - (2026.01.30)

Since the official groundbreaking ceremony on April 27th, 2025, the construction of ANAVA SAMUI has been progressing steadily and according to schedule. As of 30 January 2026, the construction updates are as follows:

  • Building D: Second-floor masonry work is 80% completed.
  • Building J: Second-floor internal scaffolding installation completed.

  • Building K: Second-floor slab concreting completed; Third-floor column rebar tying completed.

  • Secondary Structure & MEP (Mechanical, Electrical & Plumbing) Works: 

  • Bathroom guide walls and wall rebar anchoring works: Completed in Buildings A, B, C, D, E, F, G and H.

  • Ventilation & plumbing works

    Ventilation vertical pipes completed in Buildings C, D, E, and F,  50% completion in Building A; Rainwater vertical pipe installation 50% completion in Building A, 90% in Building E, and 100% in Building F; Bathroom piping works are completed in Buildings E and F, and 50% completion in Building A.


Please see the latest on-site construction photos below for a visual update:

Building A: Drainage pipe installation.

A-1.png

Building D: Second-floor masonry works.

D-1.png

Building J: Second floor internal scaffolding installation; Second floor column rebar tying.

J-1.png

J-2.png

Building K: Second-floor slab formwork; Second-floor slab rebar tying; Second-floor slab concrete pouring.

K-1.png

K-2.png

K-3.png

ANAVA SAMUI remains committed to maintaining high construction standards and ensuring quality at every stage of the project.

Thank you for your continued trust and support!


ANAVA SAMUI
Together, shaping the future of island living.