ANAVA SAMUI Construction Progress Update - (2025.07.21)

Since the official groundbreaking ceremony on April 27th, 2025, the construction of ANAVA SAMUI has been progressing steadily and according to schedule. As of July 21st, here is the latest update on the construction status across different buildings:

  • Building A: Concrete pouring of the 3rd floor slab has been completed.

  • Building B: Concrete pouring of the 2nd floor slab has been completed.

  • Building D: Rebar installation for columns from 2nd to 3rd floor is completed. 40% of formwork setup for the 3rd floor slab is done.

  • Building H: 50% of embedded MEP works and termite control piping for the 1st floor have been completed.

  • Building G: Raft foundation concrete has been fully poured.

  • North side of Building A: Installation and backfilling of the drainage pipeline have been completed.


Please see the latest on-site construction photos below for a visual update:

Building A: Beam and slab formwork installation on the 2nd floor roof, column formwork from 2nd to 3rd floor, rebar installation and embedded MEP works on the 2nd floor slab, and concrete pouring of the 2nd floor slab.

A1.png

A2.png

A3.png

Building B: Rebar installation and embedded MEP works on the 1st floor slab, concrete pouring of the 1st floor slab, and rebar installation for columns from 2nd to 3rd floor.

B1.png

B2.png

B3.png

Building D: Rebar installation for columns from 2nd to 3rd floor, formwork setup for the 2nd floor slab, and formwork assembly for columns from 2nd to 3rd floor.

D1.png

D2.png

Building F: Foundation excavation and concrete pouring for redesigned layout footings.

F1.png

F2.png

Building G: Foundation rebar installation and concrete pouring.

G1.png

G2.png

ANAVA SAMUI remains committed to maintaining high construction standards and ensuring quality at every stage of the project.

Thank you for your continued trust and support!