ANAVA SAMUI Construction Progress Update - (2025.06.20)

Since the official groundbreaking on April 27th, 2025, the construction of ANAVA SAMUI has been progressing steadily. As of June 20th, 2025, here is the current status across the various buildings:

  • Building A: Ground beam concrete pouring, termite protection pipeline embedding, MEP rough-ins, and backfilling have been completed. Rebar work for the first-floor columns is 50% complete.

  • Building B: Basement wall and column rebar work has been completed. Slab and beam rebar and formwork for the basement ceiling are approximately 80% complete.

  • Building D: Ground beam formwork and concrete pouring are 50% complete.

  • Building F: Lean concrete for ground beams has been poured, and 80% of the rebar installation is done.

  • Building H: Rebar work for ground beams has been completed.


Please see the latest on-site construction photos below for a visual update:

Building A: MEP installations, termite protection, and floor backfilling

Image

Image

Image

Building B: Rebar installation for basement walls and columns, formwork setup, and beam rebar work

Image

Image

Image

Image

Image

Building D: Ground beam formwork and concrete pouring

Image

Image

Building F: Layout surveying and ground beam rebar work

Image

Image

Image

Building H: Ground beam rebar installation

Image

ANAVA SAMUI remains committed to maintaining high construction standards and ensuring quality at every stage of the project.

Thank you for your continued trust and support!


ANAVA SAMUI
Together, shaping the future of island living.

A total of 1 page 1 data