ANAVA SAMUI Construction Progress Update

Since the official groundbreaking on April 27, 2025, construction across various buildings of ANAVA SAMUI has been progressing steadily. As of May 29, 2025, the construction updates are as follows:

  • Building A: First floor ground beam cushion concrete has been completed

  • Building B: Slope protection work has been completed

  • Building D: Foundation retaining walls and backfilling have been completed

  • Building F: Foundation raft steel reinforcement has been completed

  • Building H: Foundation short columns concrete casting has been completed

Below are on-site construction photos for a more direct understanding of the progress:

Building A: Ground beam cushion concrete for the first floor

Image

Building B: Slope protection

Image

Building D: Short columns concrete casting, short columns formwork, retaining wall masonry

Image

Image

Image

Building F: Steel reinforcement, steel bar binding

Image

Image

Building H: Raft foundation concrete casting, layout marking, short columns formwork

Image

Image

Image

Image

ANAVA SAMUI remains committed to high standards and quality construction, and we sincerely thank all our valued clients for your continued attention and support!


ANAVA SAMUI

Together, shaping the future of island living.