ANAVA SAMUI Construction Progress Update
Since the official groundbreaking on April 27, 2025, construction across various buildings of ANAVA SAMUI has been progressing steadily. As of May 29, 2025, the construction updates are as follows:
Building A: First floor ground beam cushion concrete has been completed
Building B: Slope protection work has been completed
Building D: Foundation retaining walls and backfilling have been completed
Building F: Foundation raft steel reinforcement has been completed
Building H: Foundation short columns concrete casting has been completed
Below are on-site construction photos for a more direct understanding of the progress:
Building A: Ground beam cushion concrete for the first floor
Building B: Slope protection
Building D: Short columns concrete casting, short columns formwork, retaining wall masonry
Building F: Steel reinforcement, steel bar binding
Building H: Raft foundation concrete casting, layout marking, short columns formwork
ANAVA SAMUI remains committed to high standards and quality construction, and we sincerely thank all our valued clients for your continued attention and support!
ANAVA SAMUI