ANAVA SAMUI | Latest Project Progress (November 15, 2026)
Precision in every detail, steady progress across the board. ANAVA SAMUI continues to uphold uncompromising engineering standards and superior craftsmanship. As of mid-November, balcony aluminum sliding doors and ceiling installations have reached 100% completion across multiple buildings, exterior AC louver grilles are nearly complete, Building M's secondary structure has wrapped up, and Building N's superstructure formwork is advancing rapidly.
Heartfelt gratitude to all our valued owners and partners for your ongoing confidence and support! As of November 15, 2026, the building-by-building construction milestones are as follows:
Project Progress as of November 15, 2026:
Building C: Balcony glass balustrade installation 90% completed; balcony aluminum sliding door installation 100% completed; interior and balcony ceiling installation 100% completed.
Building D: Balcony glass balustrade installation 95% completed; balcony aluminum sliding door installation 100% completed; bathroom tiling 100% completed; balcony floor tiling 100% completed; interior and balcony ceiling installation 100% completed; outdoor AC unit aluminum louver installation 90% completed.
Building E: Balcony glass balustrade installation 90% completed; balcony aluminum sliding door installation 100% completed; interior and balcony ceiling installation 100% completed.
Building F: Balcony glass balustrade installation 95% completed; balcony aluminum sliding door installation 100% completed; balcony floor tiling 100% completed; outdoor AC unit aluminum louver installation 90% completed.
Building M: Secondary structural work 100% completed.
Building N: 1st-floor formwork installation 80% completed.