ANAVA SAMUI | Latest Project Progress (October 31, 2026)

Uncompromising standards, measurable milestones. ANAVA SAMUI continues to drive site development with meticulous engineering and superior craftsmanship. As October concludes, interior fit-outs and architectural facade works are progressing rapidly—marked by major milestones in tiling, ceiling installations, and balcony enclosures, alongside essential sub-ground infrastructure preparations.

Warmest gratitude to all our valued owners and partners for your ongoing confidence and support! As of October 31, 2026, the building-by-building construction progress is as follows:

Project Progress as of October 31, 2026:

  • Building C: Balcony glass balustrade installation 50% completed; balcony aluminum sliding door installation 80% completed; interior and balcony ceiling installation 60% completed.

  • Building D: Balcony glass balustrade installation 95% completed; balcony aluminum sliding door installation 90% completed; bathroom tiling 100% completed; balcony floor tiling 100% completed; interior and balcony ceiling installation 100% completed.

  • Building E: Balcony glass balustrade installation 50% completed; balcony aluminum sliding door installation 90% completed; interior and balcony ceiling installation 60% completed.

  • Building F: Balcony glass balustrade installation 95% completed; balcony aluminum sliding door installation 95% completed; balcony floor tiling 100% completed.

  • Building G: Wall plastering 50% completed.

  • Building M: Secondary structural work 80% completed.

  • Building N: Ground level (Level 0) anti-termite treatment and water supply/drainage pipe embedding in progress.