ANAVA SAMUI Construction Progress Update - (2025.09.26)

Since the official groundbreaking ceremony on April 27th, 2025, the construction of ANAVA SAMUI has been progressing steadily and according to schedule. As of September 26, here is the latest update on the construction status across different buildings:

  • Building C: Concrete casting of the 2nd floor slab completed.

  • Building E: Ground floor slab concrete casting completed; rebar installation for 1st–2nd floor columns completed; 100% of formwork scaffolding for the 1st floor slab installed; 20% of slab formwork completed.

  • Building F: Concrete casting of the 2nd floor slab completed; rebar installation for 3rd–4th floor columns completed.


Please see the latest on-site construction photos below for a visual update:
Building C: Slab formwork installation on the 2nd floor, rebar installation for the 2nd floor slab, and MEP (plumbing and electrical) embedded works.
Image
Image
Image
Image
Building E: Scaffolding setup for the 1st floor slab and partial slab formwork installation.
Image
Image
Building F: Concrete casting of the 2nd floor slab and rebar installation for 2nd–3rd floor columns.
Image
Image

ANAVA SAMUI remains committed to maintaining high construction standards and ensuring quality at every stage of the project.

Thank you for your continued trust and support!